System fields contain additional project information such as Total Cost or Status. Learn below which fields in Meisterplan can be found where and how fields with financial information are calculated.
General: Fields in Meisterplan
In Meisterplan, fields contain project-specific details, e.g., Approved Total Effort or Cost Type. To manage custom details, you can create and configure additional Project Fields. System fields cannot be configured and often consist of calculated values.
System Fields: Availability in Views and Calculation
Every Meisterplan project comes with system fields that cannot be configured or deleted. They are not listed under Manage > Custom Project Fields (exception: in the Project Fields view, you can configure options for the Status system field (e.g., "critical")).
You can find an overview of pre-configured project fields in the Manage Project Fields article.
Overview: System Fields for General Information
| Field Name | Details | Available in View | Available in API | Calculation/Definition |
|
Approved Budget |
In the selected currency ($, €, ...) |
Board (Card Configuration) Portfolio Dashboard List Project Details Project Overview |
Reporting API REST AP |
Directly editable |
|
Goal ProPremium |
Defined per project |
Reports Board (Card Configuration) Portfolio Dashboard (Bar Chart, Bubble Chart, Column Chart, Doughnut Chart) List Project Details Project Overview Roadmap Team Planner (Color Scheme) |
Reporting API REST API |
Editable in the left sidebar under Goals |
| Cost Type; Project Cost Type | Must be defined for all assigned costs (roles, financial events) |
Board (Card Configuration) Portfolio Dashboard (Bar Chart, Bubble Chart, Column Chart, Doughnut Chart) List Project Details Project Overview Resource Pool (Roles) |
Reporting API REST API |
Selection field; Either OpEx, CapEx or Benefit |
| Finish Date; Finish* | Date |
Board (Card Configuration) Portfolio Designer List Project Details Project Overview Reports |
Reporting API REST API |
Directly editable; End date of a project or an allocation; required field |
| Last Changed; Project Last Changed | Date & time |
Board (Card Configuration) List Project Overview Reports |
Reporting API | Calculated; Date the project was last changed, and therefore a non-editable field |
| Name* | Need not be unique |
Board (Card Configuration) Portfolio Dashboard Portfolio Designer List Project Details Project Overview Reports Roadmap Team Planner Goals |
Reporting API REST API |
Directly editable; Name of the Project; required field |
| Notes | Maximum number of characters: 32,000 |
Board (Card Configuration) List Project Details Project Overview |
Reporting API, Rest API | Directly editable |
| Number of Projects | Number of projects in the currently selected portfolio and date range. |
Portfolio Dashboard (Bar Chart, Column Chart, Doughnut Chart, KPI) Reports |
||
| Number of Resources | Number of resources in the currently selected portfolio. Does not include Teams or Roles. Resources need not be active. |
Portfolio Dashboard (KPI) Reports |
||
| Past Allocations | In days or hours | Project Details | Reporting API | Calculated; Allocations for this project from the start of the project until today |
| Percentage of Completion | - |
Board (Card Configuration) Portfolio Dashboard (Bubble Chart) Portfolio Designer List Project Details Project Overview Reports Roadmap |
Reporting API |
Calculated;
in the Portfolio Designer and the Roadmap, you can color the project bars according to the percentage of completion; |
| Planned Allocations; Project Planned Allocations | In days or hours |
Board (Card Configuration) Portfolio Dashboard List Project Details Project Overview Reports |
Reporting API | Calculated; Sum of all allocations |
| Program | - |
Board (Card Configuration) List Project Overview "Add Project" form Project Details |
Reporting API REST API |
Name of the program a project is assigned to; editable in the "Add Project" form and Project Details view, read-only in any other views. |
| Project Manager | - |
Reports Board (Card Configuration) Portfolio Dashboard (Bar Chart, Bubble Chart, Column Chart, Doughnut Chart) Portfolio Designer List Project Details Project Overview Resource Pool Roadmap Team Planner |
Reporting API REST API |
Selection field; Every resource my be selected as project manager |
| Project Key* | For uniquely identifying a project |
Board (Card Configuration) List Project Details Project Overview |
Reporting API REST API |
Directly editable, otherwise assigned automatically; required field |
|
Priority Score Pro Premium |
Define priority score contributions in the project fields of the Single-select type as well as in the Status field |
Board (Card Configuration) Portfolio Dashboard (Bubble Chart) List Project Details Project Overview |
Reporting API | Calculated; Sum of all priority score contributions in project fields relevant to the priority score |
| Rank | - |
List Project Details Project Overview |
Reporting API |
Calculated (project's position in the Portfolio Designer); can be changed by moving the project in the Portfolio Designer
|
| Rank Category | - |
Reports Portfolio Dashboard (Bar Chart, Bubble Chart, Column Chart, Doughnut Chart) List Project Overview |
Reporting API | Calculated (project's position in relation to the Must-Have and Cut-Off lines); can be changed by moving the project in the Portfolio Designer |
| Start Date; Start* | Date |
Board (Card Configuration) Portfolio Designer List Project Details Project Overview Reports |
Reporting API REST API |
Directly editable; Start date of a project or an allocation; required field |
| Status | - |
Board (Card Configuration) Portfolio Dashboard (Bar Chart, Bubble Chart, Column Chart, Doughnut Chart) List Project Details Project Overview |
Reporting API REST API |
Single-select Field; You can change the options under Manage > Custom Project Fields |
Overview: System Fields for Financial Information
| Field Name | Details | Available in View | Available in API | Calculation/Definition |
| Actual Allocation Benefit | In the selected currency ($, €, ...) |
Board (Card Configuration) List Project Details Project Overview
|
- | Calculated; Sum of Actual Time Worked x Billing Rate per Assigned Role and Resource |
| Actual Allocation Costs + Allocation Costs until Today | In the selected currency ($, €, ...) |
Project Details |
- | Calculated; Sum of allocation costs actually incurred, calculated from the imported actual time worked plus planned allocation costs from the last booking date until today |
| Actual Allocation Costs until 'Last Booking Date' | In the selected currency ($, €, ...) |
Board (Card Configuration) List Project Details Project Overview |
- | Calculated; Sum of actual allocation costs until and including the date mentioned |
| Actual Financial Events Costs + Financial Events Costs until Today | In the selected currency ($, €, ...) |
Project Details |
Calculated; Sum of the imported actual financial events costs and planned financial events costs between the last booking date until today | |
| Actual Benefit Total | In the selected currency ($, €, ...) |
Board (Card Configuration) Portfolio Dashboard List Project Overview Reports |
Reporting API, REST API |
Calculated; Sum of all actual financial events of the type Benefit + Actual Allocation Benefit |
| Actual Costs | In the selected currency ($, €, ...) |
Project Details Reports |
Reporting API, REST API |
Calculated; Sum of actual financial events costs and actual allocation costs |
| Actual Net Value | In the selected currency ($, €, ...) |
Reports |
Reporting API, REST API |
Calculated; Actual Benefit - Actual Costs |
| Actual OpEx until 'Last Booking Date' | In the selected currency ($, €, ...) |
Project Details |
- | Calculated; Sum of actual allocation costs and past financial events costs planned as OpEx until and including the date mentioned |
| Allocation Benefit Estimate at Completion (EAC) | In the selected currency ($, €, ...) |
Board (Card Configuration) List Project Details Project Overview
|
- | Calculated; on the role and resource level: Allocation EAC x Billing Rate; on the project level: sum of the Allocation Benefit EAC of assigned roles and resources |
| Allocation Cost Estimate at Completion (EAC) | In the selected currency ($, €, ...) |
Project Details |
- | Calculated; Allocation EAC x Cost per Hour |
| Allocation Net Value Estimate at Completion (EAC) | In the selected currency ($, €, ...) |
Project Details |
- | Calculated; Allocation Benefit EAC - Allocation Cost EAC |
| Planned Allocation Costs | In the selected currency ($, €, ...) |
Board (Card Configuration) Portfolio Dashboard List Project Overview |
- | Calculated; Allocation x cost per hour |
| Approved Budget | In the selected currency ($, €, ...) |
Board (Card Configuration) Portfolio Dashboard Portfolio Designer List Project Details Project Overview Reports |
Reporting API, REST API |
Directly editable |
| Approved CapEx Budget | In the selected currency ($, €, ...) |
Board (Card Configuration) Portfolio Dashboard Portfolio Designer List Project Details Project Overview Reports |
Reporting API, REST API |
Directly editable |
| Approved OpEx Budget | In the selected currency ($, €, ...) |
Board (Card Configuration) Portfolio Dashboard Portfolio Designer List Project Details Project Overview Reports |
Reporting API, REST API |
Directly editable |
| Benefit Estimate at Completion | In the selected currency ($, €, ...) |
Board (Card Configuration) List Project Overview
|
Reporting API |
Calculated; Actual Financial Events of the Benefit type + Planned Financial Events of the Benefit Type until today + Future Financial Events of the Benefit type + Actual Allocation Benefit +Planned Allocation Benefit from last booking date |
| Planned Benefit; Project Benefit |
In the selected currency ($, €, ...) |
Board (Card Configuration) Portfolio Dashboard List Project Overview Reports |
Reporting API, REST API |
Calculated; Sum of all planned financial events of the Benefit type + Allocation Benefit Estimate at Completion (EAC) |
| Cost Estimate at Completion | In the selected currency ($, €, ...) |
Board (Card Configuration) Portfolio Dashboard List Project Details Project Overview |
- |
Calculated;
|
| Deviation of Actual Costs from Plan | In the selected currency ($, €, ...) or percent |
Board (Card Configuration) Portfolio Dashboard List Project Overview Project Details Reports |
Reporting API, REST API |
Calculated; The difference between the sum of planned and actuals costs |
| Deviation of Actual Benefit from Plan | In the selected currency ($, €, ...) or percent |
Reports |
Reporting API, REST API
|
Calculated; The difference between actual and planned benefit. |
| Deviation of Actual Net Value from Plan | In the selected currency ($, €, ...) or percent |
Reports |
Reporting API, REST API
|
Calculated; The difference between actual and planned net value. |
| Deviation of Cost EAC from Approved Budget | In the selected currency ($, €, ...) or percent |
Board (Card Configuration) Portfolio Dashboard List Project Details Project Overview |
- | Calculated; The difference between the Cost Estimate at Completion and the approved budget displayed in time unit or percent |
| Planned Financial Events Costs |
A list of all financial events is available in a project's details; in the selected currency ($, €, ...) |
Board (Card Configuration) Portfolio Dashboard List Project Overview |
Reporting API |
Calculated; Sum of all costs of planned financial events in a project |
| Future Allocation Costs | In the selected currency ($, €, ...) |
Board (Card Configuration) Portfolio Dashboard List Project Details Project Overview |
- | Calculated; Allocation costs planned in the future |
| Future Financial Events Costs | In the selected currency ($, €, ...) |
Board (Card Configuration) Portfolio Dashboard List Project Details Project Overview |
- | Calculated; Financial events costs planned for the future |
| Planned Net Value; Project Net Value | In the selected currency ($, €, ...) |
Board (Card Configuration) Portfolio Dashboard List Project Overview Reports |
Reporting API, REST API |
Calculated; Planned Benefit minus Total Planned Costs |
| Estimated Net Value at Completion | In the selected currency ($, €, ...) |
Board (Card Configuration) Portfolio Dashboard List Project Overview |
|
Calculated; Estimated Benefit at Completion minus Cost Estimate at Completion |
| Planned OpEx; Project OpEx | In the selected currency ($, €, ...) |
Portfolio Dashboard Portfolio Designer (Financial Section, Resource Section) |
Reporting API |
Calculated; Sum of all OpEx costs: financial events of the OpEx type + allocations of the OpEx type |
| Past Allocation Costs | In the selected currency ($, €, ...) |
Project Details
|
Calculated; Planned allocation costs that are in the past (if no actual time worked is imported) | |
| Past Financial Events Costs | In the selected currency ($, €, ...) |
Project Details |
- | Calculated; Financial events costs added to the project that are in the past |
| Planned Allocation Costs until 'Last Booking Date' | In the selected currency ($, €, ...) |
Board (Card Configuration) Portfolio Dashboard List Project Details Project Overview |
- | Calculated; Sum of planned allocation costs until and including the date mentioned |
| Planned Financial Events Costs until 'Last Booking Date' | In the selected currency ($, €, ...) |
Project Details
|
Calculated; Sum of planned financial events costs until and including the date mentioned | |
| Planned CapEx; Project CapEx | In the selected currency ($, €, ...) |
Board (Card Configuration) Portfolio Dashboard Portfolio Designer List Project Overview Reports |
Reporting API |
Calculated; Sum of all CapEx costs: Financial events + allocations of the CapEx type |
| Planned CapEx until 'Last Booking Date' | In the selected currency ($, €, ...) |
Project Details |
- | Calculated; Sum of allocation costs and financial events costs planned as CapEx until and including the date mentioned |
| Planned Costs | In the selected currency ($, €, ...) |
Project Details |
- | Calculated; Sum of costs planned as CapEx and OpEx |
| Total Planned Costs; Project Total Planned Costs | In the selected currency ($, €, ...) |
Board (Card Configuration) Portfolio Dashboard Portfolio Designer (Financial Section) List Project Details Project Overview Reports |
Reporting API |
Calculated; OpEx (=all allocations and financial events of the OpEx type) + CapEx (=all allocations and financial events of the CapEx type) |
Overview: System Fields for Actuals - Time Worked Information
| Field Name | Details | Available in View | Available in API | Calculation/Definition |
| Actual Time Worked | Imported using the Quick Import: Actual Time Worked |
Board (Card Configuration) Portfolio Dashboard List Project Details Project Overview |
Reporting API REST API |
Calculated; Sum of imported Actual Time Worked up until and including the last booking date |
| Approved Total Effort |
In days or hours |
Board (Card Configuration) Portfolio Dashboard List Project Details (Custom Sections and Allocation Tracker) Project Overview |
Reporting API REST API |
Directly editable; In the Allocation Tracker, the field value is compared with Planned Allocations or the Estimate at Completion. |
| Deviation of EAC from Approved Total Effort (%) | In percent |
Board (Card Configuration) Portfolio Dashboard (Bubble Chart) List Project Details Project Overview |
- |
Calculated; Estimate at Completion (EAC) minus Approved Total Effort |
| Deviation of EAC from Approved Total Effort (in time unit) | In days or hours |
Board (Card Configuration) Portfolio Dashboard List Project Details Project Overview |
- | Calculated; Estimate at Completion (EAC) minus Approved Total Effort |
| Deviation of Actual Time Worked from Plan (%) | In percent |
Board (Card Configuration) Portfolio Dashboard (Bubble Chart) List Project Details Project Overview |
- | Calculated; Planned Allocations Total minus Actual Time Worked |
| Deviation of Actual Time Worked from Plan (in time unit) | In days or hours |
Board (Card Configuration) Portfolio Dashboard List Project Details Project Overview |
- | Calculated; Planned Allocations Total minus Actual Time Worked |
| Deviation of EAC from Planned Allocations Total | In days, hours or percent |
Project Details |
- |
Calculated; Estimate at Completion (EAC) minus Planned Allocations Total |
| Deviation of Planned Allocations Total from Approved Total Effort | In days, hours or percent |
Project Details |
- |
Calculated; Planned Allocations Total minus Approved Total Effort |
| Allocation Estimate at Completion (EAC) | In days or hours |
Board (Card Configuration) Portfolio Dashboard List Project Details Project Overview |
- |
Calculated;
|
| Last Booking Date | For a project |
Board (Card Configuration) List Project Details Project Overview |
Reporting API REST API |
Calculated; Most recent date on which Actual Times Worked was imported |
| Planned Allocations until [last booking date] |
Date & time |
Board (Card Configuration) Portfolio Dashboard List Project Details Project Overview |
- |
Calculated; Sum of all allocations from the project start up to and including the last booking date |
| Future Allocations |
Per project; In days or hours |
Board (Card Configuration) Portfolio Dashboard List Project Details Project Overview |
Reporting API |
Calculated; Planned Allocations from today until the end of the project |
Overview: System Fields for Project Risks
| Field Name | Details | Available in View | Available in API | Calculation/Definition |
|
Name |
Name of the risk in the current project |
Project Details |
- |
Editable; required field |
|
Risk Key |
For uniquely identifying a risk |
Project Details |
- |
Editable, otherwise assigned automatically |
| Risk Owner | - |
Project Details |
- |
Editable; assign a resource as the contact person for each risk, this person monitors the risk and communicates any changes |
| Impact | Define options for the degree of impact, and adjust the value for each risk in the project details view |
Project Details |
- | Editable; describes how strongly a risk would affect the project if it occurs |
| Likelihood | Define options for the degree of likelihood, and adjust the value for each risk in the project details view |
Project Details |
- | Editable; describes how likely it is that a risk will occur |
| Risk Level | Define ranges for the risk level |
Project Details |
- | Editable; the risk level is automatically calculated by multiplying the impact by the likelihood |