Quickly reassign resource and team allocations when your plans and constraints change.
- Required User Rights
- Where to Find
- Replacing Resources and Teams with Other Resources or Teams
- Reassigning Resource and Team Allocations to Roles (Unstaff to Role)
Required User Rights
To edit resource and team allocations in the Team Planner, you need to be in a user group with the following rights:
- You need to have edit rights for the currently selected scenario or the Edit Plan of Record right.
- Either the right Resource Managers Can Always Edit Allocations of Their Own Resources, Teams, and Roles, or under Edit Allocations, at least the option Role Allocations.
Where to Find
You can replace allocations in both the Time Grid Mode and the Compact Mode of the Team Planner, and unstaff allocations back to the role (only in Time Grid Mode). You can also do this in the Portfolio Designer.
Replacing Resources and Teams with Other Resources or Teams
When an allocated resource or team is no longer available, and you know who you would like to replace them with, you can quickly do so in both the Time Grid and Compact Mode.
Replacing a Resource or a Team for an Entire Project (Time Grid Mode)
To replace a resource or a team for the entire duration of a project with another resource or team, select Time Grid Mode and select the desired resource or team and the project you would like to replace them on. Then, click the three dots next to the name of the project and select Replace Resource or Replace Team:
A dialogue will open that displays a list of all resources and teams with the same role, including their available capacity and skills:
The displayed resources and teams are sorted according to their capacity during the project. Only the needed capacity is displayed; this means that, for example, if you need to replace a resource or a team on 40 hours of allocation, even resources and teams with more than 40 hours of available capacity will only show 40 hours of capacity.
At the top of the dialogue, you can choose whether you want to replace the entire allocation, only the overallocation or a percentage of the allocation.
Move your mouse over an available resource or team to be shown how allocating this resource or team would affect their capacity if you were to select them.
Find details on how the capacity in this dialogue is calculated in the article Calculating Availability When Assigning and Replacing Roles and Resources.
Replacing a Resource or a Team for an Allocation Segment (Compact Mode)
To replace a resource or a team on an allocation segment with another resource or team, select Compact Mode and click the three dots at the end of the allocation segment. Then select Replace Resource or Replace Team:
The same dialogue as above will open that displays a list of all resources and teams with the same role, including their available capacity and skills. Find more details here.
Replacing a Resource for Part of a Project (Time Grid Mode)
To replace a resource or a team on a portion of a project, click the cell that you would like to replace them on. To select multiple cells, hold down CTRL as you click the desired cells. Hover over the selected cells and click the three dots in the blue bubble to open the context menu and select Replace Resource or Replace Team:
The same dialogue as above will open that displays a list of all resources and teams with the same role, including their available capacity and skills. Find more details here.
Reassigning Resource and Team Allocations to Roles (Unstaff to Role)
When an allocated resource or team is no longer available or is overallocated, but you don't yet know who you will allocate to the role, you can unstaff the allocation back to the role. The value allocated for the resource or team will be assigned back to the role. As soon as you know who can be allocated, you can allocate them using the Staff Role functionality.
Unstaffing from an Entire Project (Time Grid Mode)
To unstaff a resource or a team from an entire allocation, select Time Grid mode and hover over the three dots at the end of the name of the project. Select Unstaff to Role:
When you click the menu entry, the entire allocation will be transferred back to the role.
To only unstaff the overallocation or just a percentage of it, click the three dots at the end of a project's name and select Replace Resource or Replace Team. At the top of the dialog, select Overallocation or In Percent and click Unstaff to Role:
Unstaffing from an Allocation Segment (Compact Mode)
To unstaff a resource or a team from an allocation segment, enter Compact Mode and click the three dots at the end of the allocation segment. Then select Replace Resource or Replace Team:
The same dialogue as above will open where you can unstaff the entire selected allocation, only the overallocation or just a percentage of it. Find more details here.
Unstaffing from Parts of a Project (Time Grid Mode)
To unstaff a resource or a team from a portion of a project, click the cell that you would like to unstaff them from. To select multiple cells, hold down CTRL as you click the desired cells. Hover over the selected cells and click the three dots in the blue bubble to open the context menu, and select Replace Resource or Replace Team:
The same dialogue as above will open where you can unstaff the entire selected allocation, only the overallocation or just a percentage of it. Find more details here.