Learn which project details from Jira will be displayed in Meisterplan after linking a Meisterplan project to Jira.
Requirements
In order to be able to see Jira data for a Meisterplan project, the project must be linked to Jira. The projects that are created by importing from Jira are automatically linked to the Jira data selected during the import. You can also link Jira data to existing Meisterplan projects in the Information Panel.
Note: If you rename the Jira issue type Epic, the synchronization with Meisterplan will no longer work, as Meisterplan relies on this specific issue type.
Required User Rights
To view project details from Jira in the Information Panel, you need to have the Use right under Manage > User Groups > Integrations > Connected Tools > Project & Task Management Tools.
Task Insights
For Jira-linked Meisterplan projects, you can see at a glance when the work is projected to be completed and if the team is still on schedule. You can also see in detail which work items are part of the project, which are already done and for which there are sufficient resources allocated in Meisterplan.
To display this information, select a project that is linked to Jira and open the Information Panel by clicking the link icon in the right sidebar.
There, you can see the desired information in the Task Insights tab of the Information Panel:
This enables you to immediately see whether or not a project is on schedule.
Allocation Comparison with Meisterplan
In this section, you can see if the allocations in Meisterplan correspond to the Jira effort.
If you have matched roles and resources in Meisterplan and Jira, you will see the differences between the role and/or resource allocations in Meisterplan and the effort in Jira. Click the arrow after each entry to get a detailed comparison per role and/or resource.
If you did not match roles and/or resources in Meisterplan and Jira, you will see a comparison of the sum of all allocations with the sum of the efforts in Jira.
Adapt Allocations & Schedule
When you click the Adapt Allocations & Schedule button, the allocations of all resources, teams, and roles that deviate from the effort in Jira will be adjusted to match the effort in Jira.
-
Allocations:
- Tasks from Jira are imported into Meisterplan as flexible allocation segments per resource.
- These segments can be viewed in the Portfolio Designer with the Flexible allocation mode.
- The start and finish dates of the flexible segments correspond to the start and finish dates of the respective tasks.
- Overlapping segments are automatically summed up.
- Partially overlapping segments are split into multiple segments to ensure overlapping periods are aggregated correctly.
- If a resource is assigned to a project multiple times with different project roles, the Jira effort is distributed evenly across all allocations.
-
Resources:
- Assignees from Jira that are not yet allocated to the project in Meisterplan will be added to the project. This is only possible if they can be matched to their counterpart in the Resource Pool based on their email address.
- If no match can be found, the corresponding tasks will not be imported.
If resources, teams, or roles are assigned in Meisterplan, these assignments are not changed when allocations are adapted.
-
Start and finish dates:
- Start and finish dates are extended if tasks fall outside the project’s current timeframe.
- Start and finish dates are shortened if the period contains no allocations or only allocations with a value of 0. If there is an allocation greater than 0, its finish date becomes the project’s finish date. In other words, the shortest possible project duration is selected without deleting any allocations.
-
Incomplete Tasks:
- Tasks without an assignee in Jira are not imported because they cannot be matched to a resource.
- Tasks without dates are added before the finish date of the project:
- if there is a gap between the project finish date and the end of the last task, they are placed within that gap
- if there is no gap, the project finish date is extended by one month and the tasks are added there.
- Tasks without effort are imported with an allocation of 0.
The button is not displayed when:
- there is no deviation between the allocations in Meisterplan and the effort in Jira.
- there is no resource, team, or role match configured in the Jira link.
- the user does not have one or more of the following user rights:
- edit allocations
- edit rights for the scenario or the Plan of Record
- edit rights for the project
Task Status
In this section of the Information Panel, you can see which Jira issues are already completed, which are expected to be completed within the current allocations and which cannot be completed within the current allocations:
Click the arrow after each category to expand a list of the issues. If you have matched roles and/or resources in Meisterplan and Jira, the issues are grouped by roles and/or resources. The colored dots before an issue name show whether an issue is in progress (blue), not yet started (gray), or completed (green).
The order of the issues within a category or grouping corresponds to the sprint order of the issues in Jira or, if there are no sprints, to the order within the Jira Epic.
If you link the project to Jira using JQL, you can specify the order of the issues in the JQL query (e.g., ORDER BY "Story Points").
Completed
This category displays all Jira issues with the status category "Done" in Jira. Various statuses can be assigned to this status category, which can be configured and named in Jira. For example, there may be a status called “Done”, which is not the same as the status category of the same name. All issues that correspond to the status category "Done" will also have a green dot in front of their name.
Within Allocation
These issues are still in progress in Jira but are expected to be completed before the scheduled finish date considering a) the remaining allocation and b) the remaining estimated effort.
Outside Allocation
These issues are still in progress in Jira and cannot be completed before the scheduled finish date considering a) the remaining allocation and b) the remaining estimated effort. Increase the allocation if these issues are to be implemented before the scheduled finish date.
No Allocated Resources
If you have configured the Jira link of the project to match roles and/or resources, you will see a list of all issues that could not be matched to any allocation of this project.
For a match to be successful, ensure that the email address of the Meisterplan resource corresponds to the email address of the Jira user, and ensure that the Jira user has set the visibility of their email address to "Everyone" in their Atlassian account.
Update Project Details from Jira
In the toolbar of the Information Panel, click More Actions to unlink the project from Jira (this will not remove the Jira connection), to change epic that is linked to the project and to update the data from Jira.