Question: How does Meisterplan convert different time units? How are FTE, person days and hours related?
Answer: There are two settings which will determine the calculation of FTE, hours and person days. The basic calculation from FTE to hours depends on the standard calendar in Meisterplan. The calculation from hours to person days depends on the setting Person Day in Hours.
The conversion of days to hours (and vice versa) is calculated based on your General Settings: Under Manage > General Settings enter how many hours equal one person day in the Person Day in Hours field.
The conversion of FTE to hours (and vice versa) is based on the configuration of your Default Calendar: Go to Resource Pool > Calendars and set up your calendar, then select Use as default calendar.